vasupsustainable.blogg.se

Delay analysis in primavera p6 pdf
Delay analysis in primavera p6 pdf












delay analysis in primavera p6 pdf

delay analysis in primavera p6 pdf

Now we need to isolate the longest path from among the two float non-critical paths.Īgain, we achieve this by setting the definition of critical activities to longest path, Figure 8. Now our longest path is non-critical because all its activities have positive total float (observe the total float column), as per the total float critical activity definition and our project constraint. (Note we also reset the definition of critical activity to total float.) Our resulting schedule is in Figure 7. What about the situation where our longest path is one among many multiple float non-critical paths? To simulate this scenario we insert a (must finish by) project constraint that falls beyond the natural network logic completion date, Figure 6. So when you have multiple float critical paths set the definition of critical activities to longest path in order to uncover the true longest critical path. We now know where to look to optimize our schedule. When we recalculate the schedule with this setting, we regain our longest path, Figure 5. This is achieved by changing the definition of critical activities to longest path, Figure 4. We need to isolate the longest path from among the two float critical paths. Our longest path is not readily apparent. Okay, our demonstration only has two multiple float critical paths, but you get the point. (Note the total float column and activities with negative total float.) The longest path is hidden among a sea of multiple float critical paths. Now when we calculate the schedule we find that we have multiple float critical paths, Figure 3. Note the must finish by project constraint date in Figure 2. But the longest path becomes less obvious when we insert a project constraint that falls before the natural network logic completion date, Figure 2. It is obvious from the Gantt chart that the critical path shown in red is also the longest path through the network. It has an experimental path that is critical and an analytical path that is non-critical. We have our demonstration project schedule in Figure 1.

#DELAY ANALYSIS IN PRIMAVERA P6 PDF HOW TO#

This Primavera P6 EPPM release 16.1 article demonstrates how to isolate or unmask the true longest path from among multiple critical or non-critical float paths in support of schedule compression. And schedule optimization requires isolating the longest path through the network from among multiple critical and/or non-critical float paths.

delay analysis in primavera p6 pdf

Longest path critical activity delays are important to note as they will delay the entire project. So a total float critical activity delay may or may not affect schedule completion: depending on the reason for its critical status. However, a total float critical activity delay may affect either an activity constraint date or the project completion date. A longest path critical activity delay will postpone the entire project. So an activity is critical either by its total float or by its position falling along the longest path. Any activities that fall along the longest path are flagged as critical. Activities that have total float less than or equal to a defined amount of time, typically 0-days, are flagged as critical. Well, in fact, there are two ways to define critical activities in Primavera P6 Enterprise Project Portfolio Management (EPPM).

delay analysis in primavera p6 pdf

But an activity that is critical does not necessarily mean it falls on the longest path. The term “critical path” is often used to refer to the “longest path”. Further – activities along the longest path should be adjusted to support schedule compression and optimization efforts. The longest path through the schedule is a key concept. Primavera P6 EPPM Multiple Float Paths and the Longest Path














Delay analysis in primavera p6 pdf